The basic main equipments involved in a Co Gen Plant is basically consisting of:-
a) Gas Compressor
b) Gas Turbine
c) By-Pass Stack
d) Boiler and Furnace
e) Ducting for Economizer
f) Economizer
g) Absorption chiller
Work at installing the equipments at a factory in Thailand. These pictures are all courtesy by Euroasiatic (Thailand) Co.,Ltd, machine makers and main contractor for supplying the whole CoGen Plant. All installation of equipments are carried out by other contractors except for the absorption chiller which was carried out by Extreme Vision Engineering.
Due to the extremely tight nature of the factory layout, work was not as easy as it seems to carry out the installation works.
The first equipment to be shifted in is the furthest from the main incoming, ie the economizer and the ducting.
Elbow duct to join the horizontal outlet from furnace to inlet of economizer.
Once this two equipments are installed, next comes the Boiler, capacity 50 Ton.
The furnace and Boiler connection has 3 connections of piping, 2 at the top and one at the bottom and these connections are welded and X-Ray 100% for PT test to ensure no leakage occurs.
Next comes the bypass stack between the furnace and gas turbine.
Finally, the Gas Turbine is the last equipment to be brought inside the plant.
In addition, other machines and equipment involves absorption chiller.
Cooling Tower Pumps and Pipings.
And Compressed Air Tanks complete with Piping.